Update - 7/19/19
Next week the contractor will begin landscape restoration and install the new cured-in-place liner on the old sanitary sewer main. Landscape restoration and contract punch list items will continue into early August.
Next week the contractor will begin landscape restoration and install the new cured-in-place liner on the old sanitary sewer main. Landscape restoration and contract punch list items will continue into early August.
Anticipated construction work for the week of July 22-26:
East Side Streets
West Side Streets
The Contractor will be re-seeding parkways in August to establish proper grass growth. Until that time, they will be performing periodic weed and erosion control management.
Anticipated construction work for the week of July 8-12
East Side Streets
West Side Streets
The project has reached substantial completion.
Our tree trimming contractor has already selectively removed some of the trees between Route 31 and Sedgewick Circle. The clearance of trees in the rear yards of the houses along Millington Way will begin in early July. Residents on Millington who have any property (swing sets or sheds) in the easement, may be contacted to move such on a case-by-case basis.
Work will continue to progress on Deville Lane through the week of July 1st.
Anticipated construction work for the week of July 1-5
East Side Streets
West Side Streets
Upcoming Construction Schedule (Weather Pending)
July 1 – July 5: Pour new concrete sidewalks.
July 8 – July 12: Pour new concrete curb and concrete driveway aprons.
July 15 – July 18: Fine grade roadway, pave asphalt binder and surface. Pave asphalt driveway aprons.
On Monday, July 1st and Tuesday, July 2nd, utility repairs will take place on Illinois Street between 1st Street and the bridge. To facilitate this work, on Monday, July 1, Illinois will be closed to eastbound traffic and westbound traffic will be reduced to one lane.
Illinois Street will be fully open to traffic at the end of the work day on Monday, July 1.
On Tuesday, July 2, eastbound traffic will be shifted north. The road will be fully open to traffic by the end of the day.