Update - 7/29/16

Below is the update through August 5.  Weather conditions are not looking favorable over the next week, so the schedule may adjust accordingly. The paving stage of the project will be starting several locations.  As part of this process the existing pavement will be milled off, fresh oil will be placed on the roadway, the first layer of asphalt will be placed, the existing structures in the roadway will be adjusted to the final grades and final paving will take place.  This process may take a few weeks and the anticipated schedule is noted below. During the paving operations no parking will be allowed on the street while work is taking place.  Please park your vehicle on your driveway or on an adjacent side street between the hours of 7am to 6pm.

      West Side Streets

  • Fellows Street & S. 6th Street – Yet this week it is anticipated that the contractor will begin milling the existing pavement surface and begin replacing driveway aprons.  The week of 8/1 the contractor should finalize driveway aprons, pavement patching, placement of the first layer of asphalt and adjustment of the existing roadway structures.  S. 6th Street will continue work on the water services.
  • Ash Street & Pine Street - Yet this week it is anticipated that the contractor will begin milling the existing pavement surface and begin pavement patching.  The week of 8/1 the contractor should finalize driveway aprons, pavement patching, placement of the first layer of asphalt and adjustment of the existing roadway structures.
  • South 15th Street – Pending the schedule at other locations this week it is possible that the contractor may begin milling the existing pavement this week.  If not, milling will take place the week of 8/1.

      East Side Streets

  • Highgate Course Area – Starting the week of 8/1 the contractor will replacing the driveway aprons, milling the existing pavement, pavement patching and pending the overall schedule may begin placing the first layer of asphalt.
  • Industrial Drive – The week of 8/1 utility work will take place.
  • Kautz Road – The week of 8/1 the contractor will begin pavement milling and adjustment of utility structures.  If the schedule allows the contractor may place the first layer of asphalt the week of 8/1.  Please note that the Union Pacific Railroad (UPRR) is planning on replacing the rail crossing on Kautz Road between Ohio Avenue and Stern Avenue.  They have indicated that this work should take place the week of 8/1 or 8/8 and will require a detour route around the area.  Once we have more information from the UPRR we will make sure to post additional information on the website.
  • Van Buren Avenue – No work anticipated the week of 8/1.