1/11/19 Update

  1. Steel is 90% up. Phase 1 is complete.
  2. Framing and roofing begin this week.
  3. The landscaper is laying erosion blankets in the offsite areas to contain the dirt from washing on the road.
  4. Gas and electric utilities expected to be complete by the end of next week.