1/25/19 Update

  1. We have power and gas in the building
  2. Window frames are complete at the back of the garage.

  3. The ironworkers are holding the milestone date goals for taking over the east half of the building.

  4. The electrician, mechanical team, and plumber are moving fast with under slab work.

  5. Concrete pours will be happening in the next few days.

  6. The  framers are continuing to move along the north face of the building and should be complete with that area in the next two weeks.