- Second floor window instalation continues.
- The second floor slab is completely done, the majority of the framing on the west side is complete, and door framing is also starting.
- The slab at the detention area (west side of the first floor) is poured. The east half of the first floor will be poured within the next few weeks.
- Roofing is almost complete.