6/14/19 Update

  1. The interior aluminum framing for the glass walls has been installed and they are putting in the glass today. On Tuesday the final field measuring for the glass film and other interior graphics will be taking place.
  2. The garage doors are being installed with the sally port and evidence garage doors already complete.
  3. The detention area is almost ready for epoxy flooring which will then allow for the bullpen wall and associated door to be installed.
  4. The squad garage has been poured with only the ADA ramp left to put in place.
  5. The remaining metal panels are on site and are being prepped for install over the next couple of weeks. The east side is already 90% complete. The panels cover the 3M wrap you can see on the outside of the building.