6/7/19 Update

  1. The squad garage is ready and waiting to be inspected on Monday and poured on Tuesday.
  2. The detention doors are installed and the block has been filled and primed for paint. We are starting to clear out the areas where epoxy flooring will be installed.
  3. The seat walls at the front of the building are complete with the specialty lights installed.
  4. The upstairs painting is almost complete and border ceiling tiles dropped with almost all of the light fixtures in.
     

 