You are here

Project News

Update - 7/21/16

The week of July 25th, the contractor will be milling the existing pavement, pavement patching, installing the first layer of asphalt and paving fabric.  The roadway will be open to traffic with flaggers directing vehicles around the work taking place.

Update - 7/15/16

The work proposed for the week of July 18th includes:

Resurfacing Area (Division Street to Cambridge Drive) - No work anticipated.

Reconstruction Area (Cambridge Drive to Tyler Road) – The contractor will be placing the new curb and concrete driveway aprons.  The roadway in this area will continue to be closed to traffic. During this closure, all refuse collection will take place as usual. 

Update - 6/30/16

This week, the water main was successfully pressure tested.  In addition, EEI staked out the access road.  WJ Johnston will be working on getting the road graded, and they anticipate beginning the drainage swale improvements adjacent to the site at some point next week. 