12/21/18 Update

  1. Phase One Steel and joists are being set.
  2. St. Charles staff members are participating in a beam signing. Photos: https://app.box.com/s/hkk588el8ps3lvtk291cwjcz91ryr4bb
  3. Dirt is being hauled out of the west pond and is being shaped around the edges.
  4. Underground electrical installation continues.
  5. The first two bioswale seeding and blanketing are completed.

     