Update - 8/7/23

Project progress is continuing to be strong with installation of footings for features such as the digital kiosks, charging bollards, trellis foundations and seat wall installations.  Also portions of the project are beginning to be put to sub grade with the installation and compaction of aggregate base for walking surfaces and future brick paver installations. 