Update - 11/2/21
Due to the weather forecast, please note the following schedule changes associated with the Roosevelt Street roadway improvements:
Week of 10/25/21
• Site clean up
• Restore driveway access
Week of 11/1/21
• Tuesday – Mill off existing pavement
• Wednesday – Install new asphalt binder course
• Thursday – Start structure adjustments
Week of 11/8/21
• Install new asphalt surface course.
• Start parkway restoration