Update - 7/2/21
Anticipated construction work for the week of July 6 - July 9
Please Note: All work contingent on weather
Anticipated construction work for the week of July 6 - July 9
Please Note: All work contingent on weather
Work anticipated week of 7/5/21
Please note all work is weather dependent
No work on 7/5/21
Starting the week of July 6th, construction will start on Roosevelt Street. The Contractor will be milling off portions of the pavement in anticipation of the utilities being installed.
Milling operations will occur on Tuesday July 6th and are anticipated to last one day. After milling is completed, the sewer and water main installation will continue up Roosevelt Street starting at Rte. 31.
Anticipated construction work for the week of June 28 - July 2
Please Note: All work contingent on weather
Work anticipated week of 6/28/21
Please note all work is weather dependent
Pave asphalt binder on 8th Ave. and Walnut Ave.
Anticipated construction work for the week of June 21-25
Please Note: All Work contingent on weather
Please note all work is weather dependent
There will be a water shutdown on Illinois avenue on Friday the 18th to facilitate water main lowering for the new culvert.
Work anticipated week of 6/14/21
Please note all work is weather dependent
The Contractor will be backfilling the Indiana culvert, placing membrane waterproofing, and beginning to place stone for Indiana Ave.
Anticipated construction work for the week of June 14-18
Please note: All work contingent on weather
Anticipated construction work for the week of June 7-11
Please Note: All work contingent on weather