You are here

Project News

Week of November 16, 2015

The work completed for the week ending November 14, 2015 included the following:

  • Restoration of the north section from the cemetery driveway north. 
  • Installation of all water services in the middle section (from Allen Lane to Johnor).
  • The south section (North Ave. to Delnor Glen Drive) will be chlorinated and tested by the end of the week.

Scheduled work for the week ending November 21, 2015 will include:

Week of October 26, 2015

The work completed for the week ending October 24, 2015 included pressure testing of the new watermain from the Q Center south to the cemetery. 

The scheduled work for the week ending October 31, 2015 will include chlorination of the line from the Q Center south to the cemetery, inspection of new hydrants as well as flushing and testing of the new watermain from the cemetery south to just south of Allen Lane.  Once the pressure test is complete, chlorination and sampling of this line will be performed. 

Week of October 26, 2015

West Side of Fox River   

Avalon Court
Completed – Punchlist items outstanding.

8th Street and 8th Court
Completed – Punchlist items outstanding.

Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.
Completed.     

East Side of Fox River

Walnut Ave. 
Completed – Punchlist items outstanding.

Crabapple Ln.
Completed – Punchlist items outstanding.

S. 10th Ave.
Completed – Punchlist items outstanding.

Week of October 19, 2015

The scheduled work for the week ending October 24, 2015 will include inspection of new hydrants as well as pressure testing of the new north portion of water main from Q Center south to the cemetery.  Once the pressure test is complete, chlorination, flushing and sampling of the line will be performed. 

Week of October 12, 2015

West Side of Fox River

Avalon Court
Completed – Punchlist items outstanding

8th Street and 8th Court
Completed – Punchlist items outstanding

Greenwood Ln., Mockingbird Ct. and Oxmoor Ct.
Completed    

East Side of Fox River

Walnut Ave.
Completed – Punchlist items outstanding

Crabapple Ln.
Completed – Punchlist items outstanding

S. 10th Ave
Completed – Punchlist items outstanding

Stone Dr. and DuKane Dr.

September 30, 2015

The contractor will begin work next week to start to remove the trees necessary to complete the streambank restoration work. In the following weeks they will be working on grading the channel and banks and installing stabilization measures along the creek.

Week of September 28, 2015

Due to the scope and complexity of this project, weather delays, and some unforeseen circumstances, project completion has been pushed back to later this fall. The contractor has worked to make some repairs to he temporary patches on N. 5th Avenue to provide a smoother driving surface. They have also worked to clean up the right-of-way and other work areas, removing debris and construction materials that will are not needed for future work. The contractor will continue to work on the watermain along N.

Pages