Week of July 22, 2013

Construction activities associated with the new bridge near Powis Road are expected to conclude in the next two weeks.  Work at the bridge is expected to be completed by July 30, 2013.  The Contractor is continuing with work activities associated with the placement of the approach sections of the roadway to the new bridge. These work activities are expected to be completed by August 9, 2013.

To read the complete update, download the attached document.

Week of July 12, 2013

The Contractor will continue placement of the mainline bituminous sub-base for eastbound and westbound traffic from Powis Road towards Pheasant Run. This work is expected to be completed by Friday July 12, 2013.  Once this work is completed, the Contractor will begin preparing for the placement of the mainline concrete pavement for both eastbound and westbound traffic from Powis Road towards Pheasant Run. This work is expected to be completed by Monday, July 22, 2013.

To read the complete update, download the attached document.

Week of July 15, 2013

Mast arm bases, mast arms, and cable installation for the traffic signals have been installed. Concrete items such as curb and sidewalk have now been completed and pavement grinding is scheduled for mid week. Project completion is scheduled for the first week of August, 2013

Week of July 15, 2013

Utility work on South 7th Street started on July 2 and is to continue this week. Utility work will consist of repairs to water mains, fire hydrants, storm sewers, and sanitary sewers.

Concrete contractor is scheduled to remove and replace curb and sidewalk on South 7th Street late this week.

The grinding, resurfacing and striping of public parking lots at the southeast corner of Second Street (Route 31) and West Main Street, and at the northwest corner of Third Avenue and East Main Street is now complete.

For the Week of July 15, 2013

Restoration work on the Municipal Building continues on schedule this week.  Masonry work along the east elevation of the Old City Hall and South Annex building has been completed. Replacement of the limestone base and stone copings will be complete in approximately a week once the stone is delivered from the quarry. All of the scaffolding along the east elevation has been removed and the public sidewalk re-opened.

Week of July 15, 2013

Underground utility work continues with the installation of storm sewer pipe, and excavation for and installation of approximately 140 feet of 4” SDR 35 sleeve for the new gas service to the new building.

Walls for the first two floors of the south end of the building and storage tanks have been erected as well as the truck bay area.  Additional work completed aligning the exterior Aeration Basin Blowers on the equipment pad east of the existing building.

Week of July 8, 2013

Paving has been completed on South 4th Ave, Independence Ave, Concord Ct, Williams Ave, Allen Ln, Post Rd and Wing Ln. Final cleanup and parkway restoration is planned to take place on these streets this week.

Utility work on South 7th Street started on July 2 and is to continue this week. Utility work will consist of repairs to water mains, fire hydrants, storm sewers, and sanitary sewers.

Week of December 17, 2012

The Contractor is scheduling to frame and pour turn lanes, curb and gutter, driveways, and the base course for the north side and south side of East Main Street from 38th Avenue to the Kautz Road/Smith Road intersection.

To read the complete update, download the attached document.

Week of December 3, 2012

The Contractor is scheduling to frame and pour turn lanes, curb and gutter, roadway shoulders, and other miscellaneous connectors for the north and south sides of East Main Street from the east to western limits beginning Wednesday November 28, 2012. This work is expected to be completed by Tuesday, December 4, 2012.

To read the complete update, download the attached document.

Week of November 19, 2012

The bridge Contractor is expecting to complete the westbound bridge deck pour including the first approach slabs by November 21, 2012. In conjunction, the eastbound bridge deck will be poured by November 17, 2012. Following the required seven day cure time and remaining sealing work, these new lanes will be ready for the traffic lane shift.