Week of November 12, 2012

The Contractor will continue the excavation of the roadway on Atlantic Drive beginning November 14, 2012. Weather permitting this work is expected to be completed by November 16, 2012. It is anticipated that the installation of the pavement stabilization work will begin on November 17, 2012.

To read the complete update, download the attached document.

Week of November 5, 2012

Beginning Monday November 5, 2012 the Contractor will begin fine grading and placing an aggregate capping material on the northeast side of the bridge. This work will be required for the placement of the new roadway approaches to the bridge.

To read the complete update, download the attached document.

Week of October 29, 2012

In preparation for the winter shut-down conditions, the contractor will begin placement of temporary aggregate material. This material will be placed through the project limits to ensure safety and accessibility through the winter months. This work is expected to be ongoing until the anticipated November 15, 2012 winter shut-down period.

Week of October 22, 2012

Over the next few weeks the Contractor will continue with various ongoing concrete placements for such items as curb & gutters, driveways, pavement and temporary pavement sections. The Contractor will continue to focus effort on the completion of the side road merging and restoration work on the south side of East Main Street.

To read the complete update, download the attached document. 

Week of October 15, 2012

The Contractor is expected to continue with the excavation of the new roadway widening. Work is expected to be completed on Tyler Road by Wednesday of this week. Excavation work will then begin between S. 13th Avenue moving east towards the McGrath Honda Dealership. This work is expected to continue through the rest of this week being completed by Tuesday of next week.

To read the complete update, download the attached document. 

Week of September 24, 2012

The Contractor will also begin prepping and placing the subgrade and sub-base of the new roadway from Powis Road to Smith Road on the north side of East Main Street. This work is expected to take place over the next two weeks. Once the sub-base of the new roadway has been completed the Contractor will begin placement of an asphalt cap over the new sub-base.

To read the full update, download the attached document.

Week of September 17, 2012

Due to modifications to the existing grading elevations near the intersection of Kautz Road and East Main Street, the Contractor will be closing the intersection at Kautz Road and East Main Street for one day beginning Tuesday September 18 at 6:00 am. This intersection is expected to be reopened by 5:00 pm the following day.

To read the full update, download the attached document.

Week of September 10, 2012

 
The Contractor will continue working on the rebuilding of the new roadway from Powis Road to Kautz Road on the south side of East Main Street. This work is expected to take place over the new 4-5 weeks. The Contractor will continue to work on the preparation of the subgrade and sub-base materials for the new widening section from Powis Road to Smith Road.
 
To read the full update, download the attached document.

 