Update - 10/16/23
Anticipated construction work for the weeks of October 16 - October 30
Please note: All work contingent on weather
Week of October 16
Monday, 10/16/23 - Curb and sidewalk poured adjacent to the pavement replacement
Tuesday, 10/17/23 - Concrete pours in the prepared roadways sections.
Wednesday, 10/28/23 - additional pour if needed
Three days required for concrete to set-up
Week of October 23
Monday, 10/23 - remove curb, sidewalk and pavement