You are here

Project News

Update - 7/13/17

Friday, July 14th thru Friday, July 21st  -  The contractor will continue concrete curb, sidewalk and driveway replacements and begin utility repairs.  Each business with proposed driveway repairs will be contacted to coordinate the work and property access.

Update - 7/11/17

The grading for the solar site is completed, and solar panel deliveries are expected in the next two weeks.  Solar production is scheduled to begin in August or September.

Inside the substation, the majority of the site work is done and equipment for the substation is beginning to be set.  Substation target completion and in-service in spring of 2018.

Update - 7/11/17

Underground work is completed.  Roadway and sidewalks are reopened.  KDOT is working with the contractor for rework of some of the concrete in the southbound lanes that will eventually require short term lane closures.

Pages